Sunday, May 17, 2009

Need more support

One of the walls in the house has a slight settling problem, you can tell because the door in the wall doesn't shut correctly and the gap above the door is about 1/4" on one side, and the other side is about an inch or more. To fix this, I put in a new concrete footing and a support post that I will be able to lift the settled area back up to where it should be.

In this picture you can see the gap over the door, the left side has a bigger gap, so that means the right side of the door needs to be lifted up. I put the support column directly below the right edge of the door.


Nick is helping fill buckets with dirt while Zander man's his own shovel. He is standing in the hole where the footing will go. Before we started digging, the basement "ceiling" to the floor was about 6-1/2 feet, eventually I will pour a concrete floor in the basement, and when I do, I will want a full 8' ceiling height down there. So, that means the footing and post I'm putting in now, will have to be below the future floor location, or I would have to move it later. What this means now is ALOT more digging. The hole for the footing is about 3' deep, plus we began excavating the surrounding area so the hole wouldn' fill up with water when we get alot of rain. Otherwise my new metal support post would rust away. You can see the black sump crock in the background that will need to be installed BELOW the 8' mark. The end result so far, we've hauled out about 150 buckets of dirt. We've found some old clay pipe, broken glass, a marble and the strangest thing yet was in one area about a foot down we hit concrete. Whats strange about that, is at what point did someone pour a 10'x10' concrete pad in the basement, and then cover it up with a foot of dirt?? I haven't fully uncovered it, so maybe I'll be able to figure out what its for, worst case would be its a tomb with bodies in it! I'll just keep my fingers crossed there is buried treasure under there.




Here's the form for my footing, also the bottom layer of rebar to keep the concrete from cracking apart. The rebar is supported about 2" off the bottom of the hole, if you look close you can see the little wire supports.


Most of the concrete is poured and I added the second set of rebar.


Finished product, all smoothed off, just need to wait for it to dry.


The next day, I set the support post in place to make sure everything fit good. I'll give the concrete a few more days to cure and then I'll start cranking the post slowly and hopefully get everything lined back up on the door upstairs.

Tuesday, May 12, 2009

Springtime is here!

Everything is starting to grow and bloom like crazy! Birds are hatching everywhere, we've counted about 9 nests in the trees in our yard. They have anywhere from 3-5 baby birds in them each. Almost all of the trees I planted have buds or leaves as well!

The apple blossoms are in full bloom.


Baby bunny hiding out in some old ductwork I had laying next to the shed.


Mama robin laying on her babies. She was laying so flat and still!


Here's the babies she was protecting.


Another nest that had 5 babies in it, not sure what kind they are.


Check out the video:

Sunday, April 19, 2009

140 trees

My order from the conservation district came in on Friday, over 140 trees. Pines, Oaks, maples, poplars, Redbuds, Dogwood, etc. Luckily I had help planting them, my dad, Nick, Jen and I got most of them in the ground Friday night. I finished up the rest over the weekend, they are all staked and the last thing to do will be to wrap them in chicken wire so the rabbits and deer don't eat them. I chose mostly fast growing trees, some of the poplars grow 4-5' per year, the Maples and White Pines should grow a couple feet per year, and the Oaks maybe a foot or so.

Doesn't look like much when they are all wrapped and in the cart, but there is 140+ trees there.


The boys lending a hand.

Here's a row of White Pines along my back property line that my dad planted. They are about 18"-24" tall.


Hurry up and grow!

Sunday, April 12, 2009

Kids Playset

Christine has been wanting a playset for the boys, so when she found a used one on Craigslist for a decent price, she sent me to go get it. Nick and I went and partially disassembled it so it would fit in my truck & trailer and some in Nicks truck. When we got it home it was pretty easy to put back together as we had left all of the main pieces intact. The boys enjoy it so far, even though its still a little chilly out. Hopefully they play on it this summer. In the meantime I'm still making some progress on the bathroom, just nothing that has provided any interesting photos.


Wednesday, April 8, 2009

Pink and Green

Remember that bathroom I was putting in upstairs? Yeah, its been awhile since I worked on it, but in the last week I've been able to get a little bit accomplished. I started off by putting up plastic sheeting vapor barrier on all the walls. Then I put up 1/2" pink foam insulation. Last up goes the drywall, actually green board in this case, its designed to be moisture resistant to prevent mildew or damage from too many steamy baths. If my mom was decorating, she wouldn't have been able to bring herself to cover up the pink walls!

Here's looking up at the ceiling, the oval cut out is for the inset dome.


The first green board sheet goes up on the wall.
One wall down, three to go.

Sunday, March 29, 2009

Fireplace Hearth Construction

Been a little while since I posted, things have been coming along kinda slowly since I got the fireplace functional. It's easier to just light a fire and sit back, than it is to finish the job!

Here's how its looked for the last couple weeks. All the metal framing is in place as well as the ductwork.


Here's the start of the raised hearth. Those are 2x6's, so when the hearth is complete and tiled, it will be about 7-1/2" tall.


The dogs quickly found their new favorite spot, nice and warm...


Cutting the 1/2" thick, fireproof cement board with a diamond blade. This will line the walls and the hearth. Yes, if you look closely its snowing outside. Where's our nice spring weather?

Here is the hearth with 2 layers of Durock to offer extra protection from the heat. Also the first sections going up on the walls. The next pieces I will need to cut to follow the curves of the top of the fireplace.

Monday, March 2, 2009

Chimney - Up Top

Here's how things look up top now on the chimney. The new metal pipe sticks up out of the masonry about 3 inches. It is surrounded by mortar to fill the gap around it, where the opening was chiseled out. Attached on either side is an aluminum "L" bracket that was drilled and bolted into the concrete, this is where the chimney cap attaches.


"hellooooooooo".... Looking down into the new stainless chimney.


Here's the completed product with the new chimney cap to keep rain and bats out!

Monday, February 23, 2009

Fireplace Install

I've been working on installing the new fireplace pretty much non-stop lately. Worked on it all weekend from when I woke up until I went to bed at night. It started with alot of demolition, I had to cut out a 4-1/2 foot wide opening that was 8 feet tall in the living room wall. This is the wall that the old chimney ran up through.

Here's standing inside the boys bedroom looking out into the living room through the giant hole that I'm creating. Its pretty amazing how much work was actually involved in "making a hole in a wall".


Making an opening that big required cutting out some wall studs. After I supported the wall properly, I cut the studs out and then framed in a double 2x8 header that you see at the top of the photo. This header is supported on each side by 2 - 2x4 studs and carries the weight from the studs above that were cut off. You can also see a gas line and electric wire in the wall there that I had to relocate.


Here is a side view after the wall was completely removed, I also had to remove 2' off the side wall in the bedroom to maintain my proper clearance from the fireplace. On the floor I'm starting to frame out the platform the fireplace will be sitting on. You can also see the floor where I patched it up. Where the hammer is laying used to be the opening the brick chimney ran through down into the basement.


My dad and brother helped move the fireplace into position and I began installing the chimney pipe from there, the pieces just twist-lock together and about every 5 feet I install a wall clamp. I still need to build a hearth out in front of the fireplace and also frame in the walls around the fireplace with metal studs.


Up in the attic, the new chimney pipe runs up through the old masonry section I left above the roof line. Eventually I will frame this all out so the pipe is enclosed. Also you can see one of the wall straps in this pic.

Saturday, February 21, 2009

XL Delivery - Fireplace 3

The wood burning fireplace for the living room showed up the other day. Between the fireplace and the chimney sections the shipping weight was 1000 pounds! Here's the delivery truck, it was too big to back up into my driveway because he would have to maneuver between the trees alongside the drive.


After unloading, we were able to wheel the lighter pallet (300lbs) up to the porch. The heavier pallet (700lbs) had to be left down in the driveway as the truckdriver and myself couldn't pull it any farther. After he left I hooked a tow strap on it and dragged it up closer to the house with my truck.


Here's the fireplace setting in the house after 4 of us managed to get it up the stairs. It definately wasn't easy. The fireplace is a high effeciency EPA approved unit, it was just made available in the U.S. last month (Jan. 09). It was a pretty expensive unit, but the plan is that it will heat most of the house. I will run ductwork from the fireplace to the upstairs of the house and the fireplace has a large blower to distribute heat. There are glass doors not on it yet in the pic, that seal the fireplace and allow it to burn for a long time (overnight) once loaded with wood. Another reason I went with this fireplace is the cool wrought iron detail on it, the doors also are trimmed in wrought iron and it should go really good with the style of our house.

Wednesday, February 11, 2009

Gas Fire 2

We had a nice warm spell the last couple days here, yesterday it was 60 degrees out! Definately got the spring fever started. However, it will be dipping back into the 20's soon. In the meantime I ran some more gas line and fireplace #2 is up and running in the dining room. Now its nice and warm in there! Its pretty cool because the gas fireplaces are thermostaticaly controlled, so they turn on and off automatically to keep the room the right temperature.


A closer view.


Also was working on tearing out the fake brick that was on the floor surrounding the wood burning stove.

Sunday, February 8, 2009

Chimney - BIG project

After a chimney fire in December, the chimney had suffered some major cracking and damage from all the intense heat. It was unusable until either it was cored out and relined, or completely removed and rebuilt. I went with the latter. It took 4 men working non-stop to get all the brick torn out and removed. We went from the attic to the basement and removed about 40 feet of brick, estimated to weigh about 5000 pounds or so. The new chimney will go back in the same location, only now it will be a 9" insulated metal pipe, weighing about 250 pounds.

Here is how it started, up in the attic. Bracing was installed to support the 3' section of brick up on the roof. I wanted to maintain the original appearance from outside the house. A shiny round metal pipe sticking out of the roof just wasn't gonna cut it. I estimate the brick on the roof to be around 300lbs, so not a whole lot of weight really. It is braced with 2x8's and there will also be 2x4 bracing running down to the joists below. I calculated wind loads up to 100mph and they were relatively insignificant because there isn't much surface area sticking up above the roof. I will install some angle iron in each corner as an extra precaution, (we had a tornado in the area last year that severely damaged several houses a couple miles away).

Glen throwing down the grunt labor, ready to tackle some more buckets of brick.


Matt working near the ceiling on the 2nd floor.

Looking down from the second floor. Remus is starting to pull bricks going through the floor into the basement.


Here's what was installed to help control the dust on the 1st floor. It seemed to work pretty good. Kinda reminded me in the movie ET when they quarantined of their house...


Nice little pile of bricks. This isn't all of them either.

On a side note, I recieved an awesome package from my Aunt Carol (mismike), she sent some cool things to hang on our walls, including 2 very large ornate wooden keys. Thanks Aunt C! I'll get some pictures when I figure out where I'm gonna hang them.

Tuesday, February 3, 2009

Gas Fire

Last weekend we got a new gas fireplace for the parlor to help warm things up a little, and maybe help cut down the heating bill a little. The fireplace is a 99.9% effecient vent-free unit. It seems to be working pretty good throwing out alot of heat.

Elsewhere in my blog I've shown water lines and drain lines, now its time for some gas lines! So before we could use our new fireplace I needed to run the new lines. The line coming in from the right side in the pic is the existing supply line that runs up to the 2nd floor gas heater, it connected to the line in the picture that goes up through the floor and into the wall. I cut the pipes apart, took out the 90 degree elbow, replaced it with a tee, then added in a new shut off valve, then I connected my new line (to the left of the picture) to the other leg of the tee.

Here's the new fireplace in action (ignore the brown paneling on the walls, thats another project for another day)


Sunday, January 11, 2009

Blown in Insulation, aka, Indoor Snow

Got started on blowing insulation into the walls today. First had to make a trip down to Lansing to rent a blower and buy 15 bales of cellulose. The roads were a mess from the snow last night, somehow it had formed a layer of ice on the freeways. I saw about 6 cars in the ditch, saw one go in, and saw one truck upside down, where unfortunately they were hauling a woman on a stretcher to an ambulance. Hopefully she wasn't too badly injured.... Once I got safely back home with all the equipment, my dad and Nick showed up to help. We carried the blower upstairs into the master bathroom, from there Nick fed bales of insulation into the hopper while I operated the hose and worked on filling up the walls from up in the attic. Meanwhile my dad was drilling holes in walls that weren't accesible from the attic. It turned out 15 bales wasn't nearly enough, I didn't figure it would be, but I didn't really have an estimate of how much I needed. It took us about 4 hours to use them up, and after that we called it a day and I returned the blower. Its going to take a few more days of work and probably 30+ more bales to finish up the job. I'll try to work on it some more next weekend.

Messy pretty much sums it up. I was quickly covered in what looked like ashes.
Filling the walls in the master bathroom.
Nick stirring the hopper to break up the clumps.